Monday, July 6, 2009
Monday, June 29, 2009
Sunday, June 28, 2009
Wednesday, May 27, 2009
Saturday, April 18, 2009
Thursday, March 26, 2009
Thursday, February 19, 2009
Another MILESTONE
Pilot plant ready to receive equipment! We just came back from the site touring level 2 & 3. JKR seemed happy - they manage to keep their 3rd promise after all....Congratulations!
Thursday, January 22, 2009
Meeting at JKR site office
News update
contract expires 10/4/09
landscape not done yet
external work in progress
M&E in progress
confirm end February to receive equipment at pilot plant
new item - direct road to pilot plant to allow access for trailers with max. six wheels (must inform equipment supplier)
temporary signage - sliding type
contract expires 10/4/09
landscape not done yet
external work in progress
M&E in progress
confirm end February to receive equipment at pilot plant
new item - direct road to pilot plant to allow access for trailers with max. six wheels (must inform equipment supplier)
temporary signage - sliding type